State utility regulators have asked Mississippi Power Co. and the Sierra Club to submit proposals on how to proceed with the Kemper County coal-fired power plant.

The Mississippi Supreme Court ruled Mar. 15 that the Public Service Commission failed to lay out its reasoning clearly when it changed the terms under which Mississippi Power could build what it calls Plant Ratcliffe in Kemper County.

The Supreme Court told the PSC to clarify how it decided to allow construction of a Kemper County power plant last year.

In an order filed this past week, the PSC gave the two sides an April 2 deadline to submit proposals.

The key issue is not whether the plant is a good idea, but whether the PSC adequately laid out its rationale.


Comments are posted from viewers like you and do not always reflect the views of this station.
powered by Disqus
WTOK-TV 815 23rd Ave Meridian, Ms. 39301 Phone: (601) 693-1441
Gray Television, Inc. - Copyright © 2002-2014 - Designed by Gray Digital Media - Powered by Clickability 144639065