The Mississippi Supreme Court is hearing oral arguments Wednesday on the Sierra Club's challenge to a $2.9 billion power plant in Kemper County.

Mississippi Power Company is building a coal-fired plant, to be powered by lignite mined nearby. The project was approved in 2010 by the Mississippi Public Service Commission.

The Sierra Club argues in its appeal that the utility regulatory body didn't have enough proof that the plant was needed or that Mississippi Power could build it while keeping rates reasonable for customers.

The 582-megawatt plant near the Liberty community will convert coal into a synthetic gas, aiming to generate electricity with fewer emissions than existing coal power plants.

The plant is under construction and expected to start operation in 2014.


Comments are posted from viewers like you and do not always reflect the views of this station.
powered by Disqus
WTOK-TV 815 23rd Ave Meridian, Ms. 39301 Phone: (601) 693-1441
Gray Television, Inc. - Copyright © 2002-2014 - Designed by Gray Digital Media - Powered by Clickability 135586158 - wtok.com/a?a=135586158